Planning & Scheduling
Lesson 2 of 13 in Project Management Communication · 25 minutes
Learn how to break a project into tasks and sub-tasks, estimate time, understand Gantt charts, dependencies, and the critical path, and create a simple project schedule.
What you'll learn
- Break a project into tasks and sub-tasks
- Estimate time for tasks
- Understand Gantt charts, dependencies, and the critical path
- Create a simple project schedule
From the lesson
Planning a Workplace Project — Step by Step
Every successful project starts with a good plan. Here's how to plan a project in a Canadian workplace.
Step 1: Define the Project Goal
Before planning tasks, be clear on what you're trying to achieve. Example: "Reorganize the warehouse to improve efficiency by 20% within 6 weeks."
Step 2: Break the Work Into Tasks (Work Breakdown)
Take the big goal and divide it into smaller tasks. Example:
Phase 1: Plan - Survey the current layout: Walk the warehouse, take photos, measure sections - Get team input: Hold a brainstorming meeting, collect suggestions
Phase 2: Design - Create new layout: Draw floor plan, place equipment, get sign-off
Phase 3: Execute - Move…